Ford Windsor 28 MW Steam Turbine Generator Installation

CHA provided detailed engineering, design and procurement services for the installation of a 28.5 MW extraction condensing steam turbine generator in the existing powerhouse of the Ford Motor Company Plant. The unit was mounted on a modified existing foundation and an existing condenser was refurbished to serve the new unit. The project was carried out in a joint venture with the installing contractor.

Project Services:
  • Contract coordination for the following
    • Steam turbine generator procurement and installation
    • Auxiliary systems and equipment procurement and installation
  • Modification of existing turbine generator foundation to suit new unit
  • Engineering for the refurbishment of the existing steam condenser
  • Design of the following
    • Piping systems
    • High and medium voltage electrical systems
    • Electrical systems protection
    • Data acquisition system